of Trabzon Arsine district, where energy will be produced with the water provided from the drinking water transmission line. micro/mini hydroelectric power plant (HES) project is being implemented. Trabzon Drinking Water and Sewage Administration General Directorate (TİSKİHİDROTEM mini HEPP power plant developed by TEMSAN will be used in the project planned by )

Electricity generation from drinking water

TİSKİ will be established on an area of ​​418 square meters in Elmaalan District of Arsin district. Arsin Drinking Water Maslak-1 Micro HEPP with annual 3.885 GWh aims to produce energy. 0.610 MWm – 0.555 MWe The facility, designed for its installed capacity, will be completed at a cost of approximately 9.5 million TL.




Electricity will be produced from drinking water in Trabzon: Micro HEPP period




See Full Size


Within the scope of the project, water coming from the drinking water transmission line will be directed to turbines and converted into energy. The water, which will be transferred from the DY2 water tank to the M1 reservoir through 2501.94 meters long, 400 mm diameter steel pipes, will produce energy by operating the turbines by breaking the pressure. In this process, water will be returned to the existing drinking water line to prevent any outages.

The facility, in which a Francis type turbine will be used, will convert water at a flow rate of 170 lt/h into energy. The electricity produced will be transferred to the national grid through the autoproducer cell. One of the most important features of the project is that it allows energy production without interrupting the flow in the drinking water line. In this way, drinking water services will not be disrupted and clean energy will be produced.

TEMSAN HİDROTEM mini HEPP power plant

Designed to be used in municipal transmission and agricultural irrigation lines, drinking water treatment facilities, water tank inlets and outlets, facilities using cooling water, and sea discharge points, HİDROTEM has a structure that does not require construction and can be easily installed.

In the statement made last year, it was reported that these power plants would be used in Trabzon Arsin Municipality, Arsin Drinking Water and Treatment Plant and Zonguldak. Designed for a minimum installed power of 0.5 kW, the system can reach up to an installed power of 1 MW. This power value means that the electricity consumption of approximately 200 houses will be met. It is stated that there is a potential of over 1000 MW in Turkey where HİDROTEM can be used.






Source

https://www.enerjigunlugu.net/trabzonda-icmesuyunun-gucu-ile-elektrik-uretilecek-61806h.htm